Regional broadband network design and construction supervision
Regional telecommunications infrastructure linking access nodes in Krosno and the Municipality of Chorkówka.
Complete design documentation and construction supervision for a fibre-optic broadband network across two municipalities.
- Location
- Krosno i Gmina Chorkówka
- Client
- Gmina Miasto Krosno
- Category
- Specialist infrastructure
Context and technical scope
Construction designs were prepared for the Krosno and Chorkówka sections, followed by construction supervision during network delivery.
System purpose
Regional telecommunications infrastructure linking access nodes in Krosno and the Municipality of Chorkówka.
Completed scope of work
- complete network construction design for the Municipality of Krosno
- complete network construction design for the Municipality of Chorkówka
- planning and location procedure for the regional broadband network
- construction supervision for works in both municipalities
Installations and systems
- fibre-optic network backbone
- ducts and cable ducting
- fibre-optic lines
- access nodes
- 3.6 GHz WiMAX
Technical parameters
- Fibre-optic backbone length
- 34.024 km
- Krosno section
- 10.540 km
- Chorkówka section
- 23.484 km